Evergreen Lake Detour Map
Evergreen Lake Detour Map

Evergreen Lake Detour Map – Evergreen Lake Construction on 74

The Evergreen Lake North Trail Project was launched in response to the closure of the trail along CO 74 on the north side of Evergreen Lake between Upper Bear Creek Road and Evergreen Dam in Spring 2016. The aim of this project is to create a multimodal transportation system that will enhance bike and pedestrian facilities, while also addressing urgent drainage and stability issues, under a critical trail linkage adjacent to CO 74 on the north side of Evergreen Lake in Evergreen, Colorado.

Evergreen Lake Project

The project involves widening the trail to meet AASHTO criteria for shared use paths, improving fishing opportunities, wildlife viewing, and enhancing drainage and bank stabilization. Its ultimate goal is to collaborate with the community, stakeholders, and funders to create a long-term solution for the Evergreen Lake North Trail, thereby improving safety, accessibility, and connectivity in the area.

The Evergreen Lake North Trail improvement is a seven-year, multi-agency initiative spearheaded by the Evergreen Park & Recreation District (EPRD) and contracted to be carried out by ESCO Construction of Evergreen. The project has been primarily funded by grants and contributions from various organizations such as Denver Regional Council of Governments; Jefferson County Open Space, Colorado Parks and Wildlife, Evergreen Metropolitan District, CDOT, Great Outdoors Colorado, Colorado Department of Local Affairs, Evergreen Legacy Fund, and EPRD, with about 91% of the construction project budget coming from federal, state, and grant funding. The project is grateful for the support of the Evergreen community, stakeholders, funders, and partners.

When Does Evergreen Lake Construction Start and End?

Construction is scheduled to commence by mid- to late-April 2023 and is expected to continue until fall 2023, with working hours from 7:00 a.m. to 6:00 p.m. The project’s location near the lake’s edge involves road and retaining wall improvements, with CO 74 reduced to a single eastbound lane only between Upper Bear Creek Road and the JC-73 intersection. For westbound traffic, a detour will be in place via Meadow Drive, and the Evergreen Lake North Trail will be closed for pedestrians during construction. A trail detour around the south and west sides of Evergreen Lake will be provided.

Douglas Park Road is a residential neighborhood and is not an approved detour route, so motorists are advised to use the Meadow Drive established detour. During construction, delays of up to 10 minutes are expected, and loads wider than 12 feet will be restricted through the work zone.

Evergreen Lake Detour Map
Evergreen Lake Detour Map
Evergreen Lake Trail Detour
Evergreen Lake Trail Detour

Evergreen Lake Project:

  • Created in response to the Spring 2016 closure of the trail along CO 74 on the north side of Evergreen Lake between Upper Bear Creek Road and Evergreen Dam.
  • Aims to create a multimodal transportation system that improves bike/pedestrian facilities while fixing urgent drainage and stability issues under a critical trail linkage that is adjacent to CO 74 on the north side of Evergreen Lake in Evergreen, Colorado.
  • Improvements include widening the trail to meet AASHTO criteria for shared use paths, creating improved fishing opportunities and wildlife viewing, and providing for drainage improvements and bank stabilization.
  • Goal is to work with the community, stakeholders, and funders and create a long-term solution for the Evergreen Lake North Trail to improve safety, accessibility, and connectivity in our community.

Evergreen Lake Project Funding:

  • A seven-year, multiple-agency collaboration led by Evergreen Park & Recreation District (EPRD) and contracted to be constructed by ESCO Construction of Evergreen.
  • Funded primarily by grants and contributions from Denver Regional Council of Governments; Jefferson County Open Space, Colorado Parks and Wildlife, Evergreen Metropolitan District, CDOT, Great Outdoors Colorado, Colorado Department of Local Affairs, Evergreen Legacy Fund, and EPRD.
  • About 91% of the construction project budget comes from federal, state and grant funding.
  • EPRD is grateful for the support of the project’s many partners, funders, stakeholders, and the Evergreen community.

Work Schedule:

  • Construction is scheduled to begin by mid- to late-April 2023 and is expected to last until fall 2023.
  • Normal working hours will be from 7:00 a.m. to 6:00 p.m.

Traffic Impacts:

  • CO 74 will be a single lane for eastbound traffic only between Upper Bear Creek Road and the JC-73 intersection.
  • For westbound traffic, there will be a detour in place via Meadow Drive.
  • Douglas Park Road is a residential neighborhood and is not an approved detour, please use the Meadow Drive established detour.
  • Delays up to 10 minutes can be expected.
  • Loads wider than 12 feet will be restricted through the work zone.
  • The Evergreen Lake North Trail will be closed during construction, with a trail detour around the south and west sides of Evergreen Lake.

Orson Hill Realty

Real Estate Agents at Orson Hill Realty for Buying and Selling Your Home
Our real estate Agents and Brokers are all Realtors so you have a higher level of ethics and experience. Our staff is also Very Active in the Community – All Orson Hill Realty agents and brokers are local and love their community. We strive to keep our hands on the pulse of the community by being involved in every aspect of the area. We volunteer, have open houses, work at our schools and local sporting events.  Don’t forget to visit or get listed on our local business directory! Have a piece of mind when you hire Orson Hill Realty Realtors. Know we will handle everything in your real estate transaction professionally and ethically. The broker/owner of Orson Hill Realty is also a Realtor in Southwest Florida. We would like the opportunity to win your business. Buyers and Listing Agents…
We Want to be Your Real Estate Agents…
Real estate agents understand the importance of an online presence and the best technology for our buyers as well as our sellers. For buyers our technology is important because in this fast paced real estate market you need to be notified immediately when a home becomes available on the MLS (Our multiple listing service) You can also do a very detailed home search through our portal that is updated multiple times a day to have the newest and freshest information on homes being listed, sold and going under contract. We also push all of our listings out to a huge amount of online sources, so that you can find your new home with ease!

Leave a Comment

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply